Skip to main content

Full text of "Gold Mine 1987004"

See other formats


THE GRANITES 
GOLDMINE 

North Flinders Mines Limited 

(Incorporated In &A) 

GOLD ROOM 
OPERATIONS MANUAL 




Produced By 
Michael Hand 
(Senior Foreman) 



ACKKOVLEPGEMBITTS 

The development of the Intensive Cyanidation Procedure 
involved considerable test work. For the initial 
feasibiltiy studies much is owed to Ian McGrattln, 
consultant metallurgist. The first full scale batch 
treatments were conducted by Ron Wilson, gold room 
foreman, in consultation with Keith Goble-Garrett , 
plant metallurgist. These trial treatments resulted in 
the setting down of operational procedures as detailed 
by Ron in section 6.4c of this manual. 



The comprehensive coverage of the Vilfley table, Part 
5.3, was written by Ron Wilson. 



Rachel Chisholm very kindly prepared the cover for 
this manual. 



M.H. 



CONTENTS 



Page 



Acknowledgements. 
List of Figures. 
Introduction. 
PART I - THE STRIPPING SYSTEM. 

1 . 1 General . 

1.2 Sequence Controllers. 

1.3 Description of Stripping Process. 

1.4 Electrowinning. 

1.5 Operation of the Stripping System. 

1.6 Fault Finding Procedure for the Stripping System, 
PART 2 - THE SEQUENCE CONTROLLERS, 

2.1 Acid Vash and Rinse Steps. 

2.2 Acid Vash and Rinse Instructions and 
Output Settings, 

2.3 Stripping Sequence Steps. 

2.4 Stripping Sequence Instructions and 
Output Settings. 

PART 3 - OPERATION OF THE STRIPPING SYSTEM . 
(Step by Step Procedure) 

3. 1 General . 

3.2 Acid Vash. 

3.3 Washed Carbon Transfer. 

3.4 Reagent Addition and Pre-Treatment, 

3.5 Elution. 

3.6 Transfer of Barren Carbon to Regeneration 
Kiln Hopper. 

3.7 Electrowinning. 

3.8 Stripping System - Optimization of 
Reagent Usage. 

PART 4 - THE STRIPPING SYSTEM - FAULT FINDING. 

4. 1 Acid Vash. 

4.2 Transfer of Loaded Carbon to Elution Column. 

4.3 Reagent Addition and Pretreatment Stage. 

4.4 Elution and Carbon Cool. 

4.5 Transfer of Barren Carbon to Regeneration. 
Kiln Hopper. 

PART 5 - THE GRAVITY CIRCUIT. 



i 

(iv) 
(v) 



5. 1 General. 

5.2 The Spirals, 

a. Optimum Operating Conditions. 
The Static Distributor. 



1 
2 
3 
5 
5 
5 



8 

9 
10 

11 



b. 
c 
d. 
e. 



The Primary Spiral. 
The Cleaner Spiral. 
Maintenance of the Spirals. 



12 
12 
13 
13 
15 

15 
17 

19 



2 
2 
2 

2: 

2 



2 

2 
2 

2 

2 



PART 5 



- THE GRAVITY CIRCUIT. (Continued) 



5.3 The Vilfley Table. 

a. General Description. 28 

b . The Head Hot ion . 29 

c. Adjustment of Deck. 30 

d. Action of Table. 31 

e. Operation of Table. 31 

f . Maintenance of Vilfley Table. 32 

5.4 Starting Up and Shutdown Procedure for 

the Gravity Circuit. 33 

PART 6 - PREPARING OF GRAVITY CONCENTRATES FOR SMELTING. 

6. 1 General. 34 

* 6.2 Amalgamation. 34 

6.3 Acid Digestion. 34 

6.4 Intensive Cyanidation. 

a. General, 37 

b. Description af Plant. 37 

c. Operation of Plant. 38 

d. Further Considerations. 40 

PART 7 - PREPARING CATHODE VOOL FOR SMELTING. 

7 . 1 General . 42 

7.3 Removing the Wool. 42 

7.3 Acid Digestion of Wool. 42 

7.4 Drying the Cake. 43 

PART 8 - SMELTING. 

8 . 1 The Furnace . 45 

8.2 Crucibles Used. 45 

8.3 Moulds Used. 46 

8.4 Fluxes Used. 46 

8.5 Smelting Procedure. 47 

8.6 Points to Watch. 48 

PART 9 - CARBON REACTIVATION. 

9. 1 General. 49 

9.2 Start Up Procedure. 51 

9.3 L.E.D. Readouts. 51 

9.4 Shutting Down the Kiln. 53 

9.5 Adjustment of Rate of Carbon Discharge. 53 

9.6 Adjustment of Vibrator Intensity. 53 

9.7 Points to Watch. 54 

PART 10 - GOLD ROOM GENERAL. 

10. 1 Other Gold Room Duties. 55 

10.2 Security. 55 

10.3 Safety. 57 

10.4 Reagents - Their Effects on Human Beings, 

, First Aid Requirements, Handling and Disposal. 59 

REFERENCES 68 



Civ) 



LIST OF FIGURES 



fc.-. » 



Fig. 

1. 

2. 

3/ 

4. 

5. 

6. 

7. 

8. 

9. 
10. 
11. 
12. 
13. 

14, 

15. 

16. 
17. 
18, 
19. 
20. 



Flow Diagram of the Stripping System. 

Control Panel for the Stripping System. 

Carbon Fill Selector , 

Mill/Gravity Circuit Flow Diagram. 

The Gravity Splitter Box. 

The Static Distributor. 

The Spiral Discharge Splitters. 

The Vilfley Table. 

The Vilfley Table Head Motion. 

The Vilfley Table Stroke Pattern. 

The Vilfley Table Rocker Pockets. 

The Vilfley Table Tilting Mechanism. 

The Vilfley Table - Inverse Classification 
and Stratification, 

The Vilfley Table - Lines of Separation. 

The Vilfley Table - Concentrate Launder 
and Splitter. 

The Intensive Cyanidation Pilot Plant. 

The Decant Platform. 

The Barring Furnace, 

The Carbon React! vat i on Kiln. 

The Carbon Reactivation Kiln Control Panel. 



Page 
4 
6 
12 
24 
25 
26 
27* 
28 
29 
29 
30 
30 

31 
32 

32 
36 
42 
45 
50 
52 



i 

n-«Sf*.,...^.^ B | |f ... 



(V) i 



INTRODUCTION 



was 
to 



The Carbon- in-Pulp technique as practiced at The Granites 
initially introduced into the gold processing industry so as 
by-pass the counter current decantation and filtration steps o± 
the Merril-Crowe cyanidat ion-zinc cementation procedure. 

Early development was hampered by a lack of suitable carbon 
offering good activity, mechanical strength and satisfactory 
price. 

With the gold price rise of the seventies, the C.I. P. process 
has developed rapidly and there has been a rapid growth in the 
number of C.I. P. plants along with an equally rapid growth in 
technology and innovations in plant practice. 

It is now generally accepted that the C.I. P. procedure offers 
substantial savings in both capital and operating costs over the 
Merril-Crowe procedure at low head grades (<15g Au/tonne). The 
C.I. P. procedure has in fact made ore reserves with head grades 
of <5g Au/tonne commercially viable and many of the more recent 
developments are based on such reserves. 

At The Granites head grades of >10g Au/tonne are commonplace and 
the nature of the feed is such that this plant would be 
hard-pressed to achieve good recovery, without a substantial 
drop in the rate of production, but for the improved efficiency 
of the gravity circuit. 

It has been possible to reduce the number of strips each week 
and this has led to substantial savings in the use of reagents, 
gas and potable water , 

Success in the production of gravity concentrates has prompted 
investigation into alternative methods of treating concentrates 
for smelting so that the present practice of Acid Digestion, 
along with its inherent dangers and operator discomforts, may be 
dispensed with. 

Current experiments with Intensive Cyanidation have met with 
considerable success and if problems relating to the subsequent 
extraction of gold from the loaded Intensive Cyanidation product 
are overcome, this method could well supersede Acid Digestion. 

This manual has been compiled in an attempt to familiarize all 
gold plant personnel with gold room operations and developments 
and in particular, to give C.I. P. plant operators and 
maintenance personnel, a better understanding of the areas of 
gold room operations in which they are directly associated. 



FART 1 - THE STRIPPING SYSTEM 



1 . 1 General 

The Anglo American Research Laboratories (AARL) stripping 
system used at The Granites has two definite advantages when 
compared with its most common counterpart, the Zadra system. 
It is much less expensive to operate and it produces a 
cleaner stripped carbon. It is however very reliant upon the 
availability of an abundant supply of good quality water and 
its water usage is far greater than that of either the Zadra 
.system or the mare recently developed solvent stripping 
system. 

The stripping of gold from loaded carbon here involves two 
basic steps; Acid Washing and Elution. The elution step may 
be further divided into two major stages; carbon 
preheat and elution" proper . 

At The Granites a separate column is provided for acid 
washing. The advantages of this are dubious in that there 
would be more than enough time in a twenty four hour period 
for both steps to be completed in one column. In any case the 
potable water system here does not cater for the running of 
both steps at the same time. Much greater benefit would have 
been derived from the provision of an additional eluate tank 
as it is in the later electrowinning stage that most of the 
present hold ups occur. 

a . Acid Washing 

This involves the soaking of the loaded carbon in a 3% HCL 
solution in order to remove impurities such as ca lcium, 
copper and magnesium which can impede both the elution step 
and the later adsorption of gold onto the carbon after it has 
been returned to the C.I. P. circuit. Acid washing of carbon 
is in fact used as a temporary substitute for thermal 
reactivation of carbon in some plants. 

b. Preheat Stage 

During this stage a 2% caustic/3% cyanide solution mixture is 
re-circulated through the loaded carbon in the elution column 
until such time as a predetermined "top of column' 
temperature is reached. By this time most of the gold and 
silver on the carbon will have been desorbed into solution 
and both the carbon and the solution will have reached an 
optimum temperature for the subsequent elution proper. 

c . Elution stage 

During this stage the gold and silver desorbed off the carbon 
during the preheat is washed out of the column into the 
eluate tank. This stage takes 2 1/2 hours and involves the 
use of 5 bed volumes of potable water <21.6 cubic metres). 
The critical factor during this stage is temperature. It has 
been found that the optimum "top of column* temperature is 
around 110~c 




1 . 2 Sequence Controllers 



The goldroom uses the Anglo-American Research Laboratories 
stripping system to strip gold from loaded carbon in batches 
of approximately 1.9 tonnes. The process is fully automated 
and controlled by electronic sequence controllers which 
switch both pumps and valves for each step. 

The controllers can be over-ridden to stop or reset a cycle 
or to start again, at any point. It should be remembered that 
no feedback to the controllers is provided and hence a signal 
for a pump to run or a valve to open does not necessarily 
mean that the item is operating. This can be confirmed by 
visual inspection at the pump or valve. Likewise it should be 
remembered that the control lers will not operate if a local 
stop switch is depressed. <See fig. 2 on page 6) 




Although the sequence controllers govern 
the various stripping stages it is 
essent ial to monitor the plant on a 
regular basis so as to ensure that all 
equipment is operating properly and that 
desired temperatures are being reached 
and maintained within the time 
limitations set on the controllers. Here 
goldroom foreman, Ron Wilson, checks the 
panel prior to start up. 



-3- 



li3 TteRcriDtlon nf the Strippin g F rnnnB. (See fig- 11 

*' CarbofTs loaded into the acid wash column from the loaded 
carbon surge hopper by opening the main inlet valve AV 401^ 
carbon surge * « * nf f through a screen and valve 

Excess water and air are bled off througn a ^ hopper. 
AV 414 to either the leach area sump or the failings Copper. 
After fillinjr, the main valve AV 401 is closed and dil^ 
S^rocnior^kcid is injected into the bottom of the column 
via valve AV 403 Displaced water "o^*^,^ ho * per . 
the column through valve AV 414 to ed B int o the 

After acid injection and soaking. wM*r is pu p 
bottom of the column via valve AV 404 and as 
' through the column to exit via valve AV 414, it rinses 
the acid, 

b . Transfer to F.luti on Column transferred to the 

A f e t i ri roiuL th Wat a e r r b i n s J3JST2E column 

line via valve AV 402 and the carbon is forced along tne 
iine through valve AV 422 into the elution column. WJf^* 
„a"r flowl out of that column ttomgtt. inlin. filter, 
via valve AV 415 into the potable water tank. 

NaCH <2 to 3%) and Na5S C2*> to the column via valve AV 410^ 
Displaced water flows out of the top of tl« cOl«« 
the P inline filter, along the pregn-nt solution line to 
heat exchanger to exit via valve AV 410 
tank. 

jj.4.j~„ »V 416 closes and the elution 

After reagent ^dition v a ive AV 416 c by 

water pump recirculates tne so-lui-x AV 40 9 up 

pumping it via the Xt"S v. « AV 460 back to the 
through the f » ^ f ^ h t solution as it 

rasres P th P rourh ;he\ert a :xchan e g d er from thermal which is 

whlcnhTdJirfd -top of the column' temperature £ould *• 
~ + + *i-n<*d Bv this time most of the gold will nave pw« 

preheat and subsequent elution stage so as 
desired operating temperatures. 

d. Elution and Carbon Cool +>1 _ rotable 

During the elution cycle, water is drawn from the P°^^ 
w tlAank and pumped through the heat -changer via valve 
AV 409 into the column. The water then flows up £rougn 
column, taking with it gold ^ at has ^ f Elution 
solution during the preheat stage. This pregnan 
then flows out of the column through the inline filter and 
the heat exchanger, then via valve AV 416 to 



-5- 



tank. This stage continues until five bed volumes of water 
have passed through the column (2.5 hours) after which 
desired barren carbon assays of -30g Au/tonne should be 
achieved. 

At the end of the elution stage the thermocal heater stops 
and an additional amount of KaOH is pumped into the eluate 
tank via valve AV 420, this bringing the pH of the eluate 
solution up to the desired level. Potable water then 
continues to flow through the system as per the elution 
stage for another twenty minutes, this taking some of the 
heat out of the carbon and the thermocal. The thermocal 
pump operates for another two hours after the end of the 
carbon cool stage, this aiding the cooling down of the 
heater. 

e. Transfer of Barren Carbon to the Regeneration Kiln Hopper 

At the end of the carbon cool stage, water is pumped into 
the column via valve AV 409 so as to maintain pressure 
within it and force the barren carbon out of the column via 
valve AV 421 into the carbon transfer line. Additional water 
is injected into this line via valve AV 412 and the carbon 
is carried long the line to the dewatering screen above the 
regeneration kiln feed hopper. 

1. 4 Electrowinning 

One bed volume (thirty minutes) into the elution stage the 
eluate pump is started and pregnant solution from the eluate 
tank, is pumped up into the electrowinning cell on the first 
floor of the goldroom. It then flows back into the eluate 
tank. As the solution flows through the electrowinning cell, 
gold is plated on to the steel wool cathodes. This 
recirculation process continues for around 14 to 16 hours 
after which period of time there should be no more than -lg 
Au/tonne of eluate remaining in solution. The barren solution 
is then pumped out of the eluate tank into the process water 
tank. 



1 . 5 Operation of the Stripping System 

Details of the step by step sequence controller operation for 
the entire stripping process are out 1 ined in part 2 . This 
information is displayed on the control cubicle. The mere 
following of the instructions given in that section will not 
ensure effective stripping results as there are many 
extraneous factors which need to be taken into account. Part 
3 outlines in full detail every action required on the part 
of goldroom personnel in order to operate the plant 
successfully. Operators unfamiliar with The Granites 
stripping system should follow Part 3 directly. Loose copies 

are available. "Operation of the Stripping System - Step by. 

Step Procedure". 

1.6 Fault Finding Procedure for the Stripping System 

Should any difficulties occur during the stripping process, 
possible faults with remedial action have been detailed in 
part 4 of this manual. 



Sequence 
complete 



-6- 




CD 





a an 






31 1 
SUP 


H 




■ 


B 




« aao 


S OB 






1 V' 


■ 


B 


B 


B 


B 










unit 


■ 




B 


B 


B 




• ■ 


* ■* 


mi ; 




B 




B 


B 






All drives 
stop 




START 





1 1 lose buttons 
alop or start 
■ny atop. Tha 



only 
rvrnlnp 



o 


TFR COMPLETE 


snap cvoe 

OWLETE 


o 






















j stwppjnc cyrxt 








o 



tneucatxr l^w 






J 



CARQm TRAMSfER 




STMT STMT 




eiUATE 1AMK 






LOWLEVCl 


« 




o O 
WATER 






EKPAJ^ON IA»t 





Fig, 2 Control Panel for the Stripping Syst 



-7- 



1 STEP . . . Step display 



2 INSTRUCTION , . . Instruction 
display, The STEP display 
indicates the step number 
(or process) in progress, 
and the INSTRUCTION 
display consisting of OP, 
DATA-1 and DATA- 2 displays 
indicates the step advance 
conditions. These displays 
are used for monitoring the 
keyboard programming, as 
well as monitoring the 
program being executed, 

3 RUN . . . Run display (LED) 
The LED indicator lights 
when the START switch is 
depressed in the manual or 
automat ic mode and goes off 
when the STOP switch is 



INPUT , . . Input display 
(LED) For indication of 
input status. 



Output operation 
CLED) The LED 



5 OUT . . 
display 
Indicator lights when the 
output is not prohibited 

6 OUTPUT . , . Output display 
(LED) For indication of 
output status. The LED 
indicator also illuminates 
when the OUT ON/OUT OFF 
selector switch is set in 
the "OUT OFF" position. 

7 FLAG . . . Flag display (LED) 
For indication of flag 
status. The LED indicator 
also illuminates when the 
OUT ON/OUT OFF selector 
switch is set in the "OUT 
OFF" position. 



8 Operation switches: 

AUTO/M/E . AUTO se lector 
switch 

AUTO . . Automatic 

operation mode selection. 
M . . Manual operation 
mode selection 
E.AUTO Automatic or 

manual mode selection by 
external siRnal. 
OUT ON/OUT OFF selector 
switch . . In the OUT OFF 
position, outputs 
(including flag outputs) 
are prohibited. The OUT 
ON position allows 
outputs to be generated. 
RESET switch . ■ 

Depressing this switch 
causes the program to 
reset to step 01 and 
places the controller in 
STOP state. 
START switch 
Depressing this switch 
places the controller in 
RUN state, causing 
automatic or manual 
operation to start. 
STOP switch . . Depressing 
this switch places the 
controller in STOP state 
causing the current step 
to be held. 

9 Program Console 

Keyboard switches for 
programming. Program 
console switch must be 
turned on when programming. 

10 Battery Lid 

Battery, unit number 

setting switch for 

parrallel processing and 
program protect switch are 
mounted in 

11 Unit Number Setting Switch. 



Sequence Controller Operations 



-8- 



PART 2 ~ THE SEQUENCE CONTROLLERS 
2. 1 Acid Wash and Rinse Steps 
Refer 

Job Step Action 

I, 01 Press SEQUENCE START. "Run" and "Output" 

lights show. Manually initiate sequence by 
switching the Carbon Fill Selector switch 
to "Fill" and then "Complete" after the 
column has filled with carbon. 

^ 2. 03 Press ACID WASH RINSE START. This adds 

concentrated HCL and water to the column. 

04 Allows soak in acid. 

05 Rinses carbon column with water to remove 
acid and restore neutral pH to the 
solution 

3. On completion of the water rinse step, the 

alarm will sound. Press ALARM ACCEPT. 

4. 10 Press WASHED CARBON TRANSFER START to 

commence the transfer of carbon to the 
elution column. 

5. On completion of transfer the alarm will 

sound. Press ALARM ACCEPT and then shut 
down by pressing WASHED CARBON TRANSFER 



Note: 



Sequence is ended. 



CI) During the carbon transfer take LOADED CARBON 
samples from the sample point on the transfer line. 

<2) Complete log sheet by recording times and volumes of 
water used during this sequence. 

(3) The programme can be interrupted at any stage by 
pressing SEQUENCE STOP. It can be resumed by 
pressing SEQUENCE START. The cycle will then start 
again from the point at which it was interrrupted. 



-9- 



2. 2 Acid Wash and Rinse Instructions and Output Settings 



INSTRUCTIONS 



STEP OP. DATA DATA 
NO. 1 2 



o 



03 
O 

> 

09 



OUTPUT SETTINGS 



CO 

o 
> 



O 

> 

CO 



01 

PU 



03 
01 

10 



o 

o 

> 

CO 



p 

(X, 

p. 

0) 

I 

PC, 

C- 
Ol 

Ph 

p4 



p 
o 

CO 
O] 

Ph 
P-, 



> 



8 



a) 

i-H 
ft 



o 

10 





< 



9 



Pi 
OJ 
<H 
W 
Pi 
(C 
Pi 
H 

■a 

Pi 



10 



Pi 

a) 

rH 

o 

>s 
o 



11 



00 
01 
02 

03 
04 
05 
06 
07 
08 
09 
10 
11 
12 
13 
14 
15 
16 
17 



18 



4 
4 

9 
9 
9 

4 
9 

9 

4 

9 



1 



01 
02 
08 
10 
2 
71 
03 
00 
71 
30 
72 
04 
73 
00 
72 
73 
01 



00 
00 
00 
00 
00 
00 
00 
01 
00 
00 
00 
00 
00 
01 
00 
00 
00 



X 
X 
X 

x 



x 

X 



X 
X 
X 
X 



X 
X 



X 
X 
X 



X 
X 
X 
X 



X 
X 
X 
X 



X 
X 
X 







CODE 



ACTIVITY 



4 Instructs the programme to proceed to the next step. 

9 The programme carries out the instructions shown by the 
output setting for the time shown in Data 1 and Data 2. 
Times may be varied. 

1 This causes the programme to reset to Step 01 

2 The programme advances to the next step. 



-10- 



2. 3 Stripping sequence steps 
Fefer 

Job Step Action 

1* 01 Press SEQUENCE STAFT. The "Run" and 

"Output" lights will show on the panel. 

2. 02 Press STRIPPING CYCLE START. Cyanide 

and caustic are added to the elution 
column to soak the bed of carbon, 

05 In this cycle the strong cyanide and 
caustic solution is circulated. The 
temperature is raised from ambient to 
90-C. 

06 The stripping stage is done by 
continuously pumping water at about 
110°C through the bed of carbon in the 
elution column. The pregnant solution or 
eluate, flows into the eluate tank. 

07 An addition of caustic is made to the 
eluate . 

09 The cool rinse stage. The burner shuts 

off (The thermocal pump will continue to 
run for two hours) and cool water is 
pumped through the elution column. 

3. On completion of the stripping cycle, the 

alarm will sound. Press ALARM ACCEPT. 

4. 13 Press STRIPPED CARBON TRANSFER START to 

commence transfer of carbon to the 
regeneration kiln feed hopper. 

5. The alarm will sound at the end of the 

designated transfer time. Press ALARM 
ACCEPT. The transfer pump will still be 
operating. If all of the carbon has been 
transferred (check sight glass) stop by 
pressing STFIPPED CAFBON TRANSFER 

Sequence is ended, 

Note 

1. During the carbon transfer take STRIPPED CARBON 
samples from the sample point on the transfer line, 

2. The electrowinning cell may be started after one bed 
volume has passed through the column in step 6. 

3. Fill in the relevant information on the log sheet. 

4. To stop programme at any stage press SEQUENCE STOP 
Eesume programme by pressing SEQUENCE START 




-11- 



2 4 Stripping Sequence Instruc t ions and Output Settings 

OUTPUT SETTINGS 



r 



INSTRUCTIONS 



STEP 
NO. 



00 
01 
02 
03 



OP. DATA DATA 

1 2 



o 
> 

CO 



04 
05 
06 
07 



08 
09 
10 
11 
12 
13 
14 
15 



4 

9 




16 
17 
18 
19 




9 
9 
9 

9 

4 

9 

4 



01 
10 
72 
71 
50 
2 
8 
71 
30 
73 
02 
73 
20 
74 
03 



CODE 



4 

1 





9 


1 



00 
72 
74 
01 



00 

20 

00 

00 

00 

30 

00 

00 

00 

00 

00 

00 

00 

00 

00 

01 

00 

00 

00 



X 
X 
X 

x 
x 

X 



X 
X 
X 



0) 
-H 

n 
id 
m 

a 

01 
03 
Ph 
Ph 



> 

CO 



Ph 

CO 

03 
n, 
Ph 

Tt 
PS 

(d 

03 



03 
> 

CO 



H 

CO 



X 
X 
X 



s 

x 

X 



X 
X 
X 

X 
X 
X 
X 
X 



ACTIVITY 















01 


u 














+> 


CD 














Q) 


m 














i-H 


0) 














n 
& 


G 












& 


R 


d 












B 


U 


H 

















H 








P 




Ph 












Ph 






(D 


£3 




Ph 








rH 


r-l 


a 













as 





















u 




-H 




+> 


u 





id 










4) 


8 




o 




n 






+> 




to 






P* 






■1 


<u 


e* 


frH 

X) 




id 




Ph 


i 




•H 


■ 




o 




»Jh 


si 


£ i 


HH 


Mi 


o 




o 








P< 




03 


H 


tO 


00 




0> 


-H 


-H 




O] 




03 


w 




(h 


(_ 


> 


Ph 


> 


Ph 


Ph 




-P 


Ui 




CO 


Ph 




Ph 


CO 


CO 


5 


6 


7 


8 


9 


10 


11 


12 




















X 
















X 
















X 








X 










X 


X 


X 


X 












X 


X 


X 






X 


X 




X 


X 


X 






X 


X 




X 


X 


X 












X 




x 












X 




X 
















X 


X 














X 


X 














X 
















X 
















X 




X 












X 




X 












X 




X 
















X 









The programme carries out the instructions shown by the 
output setting for the time shown in Data 1 and Data 2. 
Times may he varied. 

Instructs the programme to proceed to the next step. 
This causes the programme to reset to Step 01 
The programme advances to the next step. 



-12- 



PART 3 - OPERATION DF THE STRIPPING SYSTEM 
(Step by Step Procedure) 



3. 1 General 

a. Check the electrowinning cell and take a sample over to the 
laboratory. Label the sample:- 



"E/V Ko. DATE TIME TAIL" 



• b. Check the potable water meter reading and the available 

potable water (off tank level indicator); and the gas 

pressure. Note these on the log sheet for the preceding 
day. 



3.2 Acid Vash 

a. After ensuring that there is sufficient carbon in the 
loaded carbon surge hopper, switch the valve control 
switch (See fig. 3) to "auto' to open the valve. 

OFF 




Fig. 3 Carbon Fill Selector 

Then put a running hose in the hopper and wait for the acid 
wash column to fill with carbon. When the carbon is visible 
in the top sight glass switch the control switch back to 
"manual' to close the valve. Check to ensure that the 
inline trash screen is clear. 

b. Make sure that the manual valve on the acid container is 
open. Record the time, the level of acid in the container 
and the reading for potable water off the meter by the 
potable water tank, on the goldroom log sheet. Press the 
"acid wash/rinse start' button on the main control panel. 

c. Check to see that the acid pump is running. As soon as it 
stops check and note on the log sheet, the acid level in 
the container. Also close the manual valve on the 
container. 

d The sequence control ler wi 1 1 automat ical ly take the 
sequence through the soak step (04) and the rinse step 
(05). At the end of step 5 the alarm will sound. Check the 
pH level of the solution from the sample point at the top 



-13- 



of the column. If it is over 5 press the "alarm accept' 
button. 

3. 3 Vashed Carbon Transfer 

a Press the "washed carbon transfer start* button on the 
control panel. Whilst the carbon is being transferred take 
samples from the transfer line sample point, every five 
minutes. Rinse the combined sample and label it:- 

"STRIP No. DATE LOADED Au content" 

b. Towards the end of the carbon transfer step the alarm will 
sound. Press the * alarm accept* button but do Not press 
the "washed carbon transfer stop' button until the acid 
wash column is seen to be empty by way of both the bottom 
of column sight glass and the absence of carbon in the 
transfer water at the sample point. 

c. After the transfer is completed and you have pressed the 
"washed carbon transfer stop* button, drain out the 
accumulator vessels by way of the two ball valves near the 
right hand side vessel and then clean out the filter bag at 
the top of the elution column. Hake sure that the filter 
bag has no holes in it and that the pliable band fits 
snugly into the ledge inside the filter housing. Also 
ensure that the steel ball has been put back inside the 
bag, 

d. Close the accumulator drain valves and also the manual 
up valve on the barren carbon transfer line. 

- 

3.4 Reagent Addition and Preheat 



a. On the log sheet, note the meter readings for the caustic, 
and cyanide pumps and also that of the potable water 
supply. 

b. On the elution control panel press the "sequence start* 
button and then the "stripping cycle start' button. This 

step will not commence if the eluate tank 'low level' light 

is not on. i.e. the tank has not been pumped out or the low 
level indicator is faulty. 

c. During the addition of reagents step (02) visually check 
that the pumps are operating and also record the meter 
readings immediately after the pumps stop. Should the 
output of either pump be drastically short of the desired 
amount (Presently 565 litres of cyanide and 100 litres of 
caustic) immediately press one of the pump stop switches 
and then reset it, This action will prevent the sequence 
controller from continuing on through the elution 
programme. It will then be necessary to add additional 



reagent by the steps outlined below; - 

Ci) Switch the controller to "manual' by way of the 
black selector switch on the main control panel 

(ii) Open auto valves AV 410 and AV 416 manually. 

(ill) Start the desired reagent pump locally and run it 
until the desired additional litres have been added 
as per meter. 

Civ) Reset the pump stop switch. 

(v) Close auto valves AV 410 and AV 416 manually. 

<vi) Switch the controller back to "auto* . 

<vii ) Press the "sequence start' button on the control 
panel. The controller will automatically continue 
on with the preheat cycle (step 05) . 

d. Check to ensure that the thermocal heater is operating. If 
it fails to start it is most likely to be because the 
thermocal pressure is too low as a^result of an airlock in 
the heater circuit. Correct this by opening the ball valve 
above the "thermocal in* line for thirty seconds or so. If 
some time has elapsed before it was noticed that the heater 
was not going, the preheat step (05) should be restarted by 
the following method: - 

(i) On the sequence control panel, switch the left 
hand side toggle switch from "auto* to "m' and the 
adjacent toggle switch from "out' to "out off . 

(ii) Press the white "reset* button next to the toggle 
switches. 

(iii) By pressing the blue "start* button step the 
controller through to step 05 again. 

(iv) Put the toggle switches back to "auto* and "out on' 
respectively. The preheat step will then 

automatically commence again and run for the full 
set time. 

e. Monitor the preheat step regularly and record both 
temperatures and pressures on the log sheet every half 
hour, the desired top of column temperature at the end of 
the preheat step varies with weather conditions, but 
during the cooler months it should reach 90^ 
approximately. If this temperature is not reached then the 
preheat step will need to be extended by switching the left 
hand side toggle switch to "m* . The preheat step will then 
over-ride the timer and continue on until the toggle switch 

is put back to auto. 



-15- 



f, Should the column pressure rise rapidly during preheat to 
above 400 kPa, it may be necessary to stop the cycle. 
Either stop the elution pump locally or press the red 
"sequence stop' button on the control panel. Then drain 
the accumulator vessels until the top of coulumn pressure 
falls below 150 kPa. Restart by resetting the pump stop 
switch and pressing the "sequence start' button on the 
control panel. 



3 . 5 Elution 

a. After preheat the controller will automatically go into the 
elution step (06). Monitor this step regularly and record 
temperatures and pressures every thirty minutes. 

b. Start the electrowinning cell after the first bed volume - 
thirty minutes running time. 

c. After one hour in the elution step (06) the following 
operating parameters are considered desirable. 

Top of column temperature around 1 10°C 



" M pressure around 130 kPa 

Bottom of column temperature around 125°C 

" " pressure around 300 kPa 

Elution water pump pressure 270 to 300 kPa 

Heat exchanger pressure in 170 to 190 kPa 

" " pressure out 150 to 170 kPa 



Thermocal temperature in around 125^0 

" " out around 122~C 

A falling top of column temperature is the best indicator 
of possible trouble caused by such things as dirty heat 
exchanger plates, thermocal heater not operating properly 
or pegged inline screens. 

3. 6 Transfer of Barren Carbon to Regeneration Kiln Hopper 

a. Open the back up manual valve on the barren carbon transfer 
1 ine . 

b. Back flush the carbon transfer line into the quench tank by 
attaching a hose to the minsup coupling behind the 
dewatering screen above the feed hopper. This step is 
only necessary if the previous lot of barren carbon was 
transferred directly into the quench tank. 

c. Close the carbon delivery valve above the quench tank. 



-16- 



d. Make sure that the dewatering screen is clean, 

e . Fill the carbon transfer 1 ine by putt ing a hose on the 
sample point and running it until an adequate flow of 
return water is evident. Do not over flush as this could 
flood the kiln. 

f. Press the "stripped carbon transfer start' button and 
throughout the transfer monitor: - 

Ci) The flow of return water. Should this decrease 
markedly, stop the elution water pump locally and 
flush the carbon transfer line again. Restart the 
transfer by pressing the "sequence start' button. 

(ii) The bottom of column pressure. Should this rise 

suddenly above 220 kPa, immediately stop the 

elution water pump and repeat the procedure 
outlined in <i> above. 

g. Take regular samples throughout the transfer and label the 
combined sample :- 

"STRIP No. BARREN, DATE , activity and Au" 

h. The alarm will sound at the end of the programmed transfer 
time. Press the "alarm accept' button and then check to 
see if the transfer is completed by:- 

<i> Looking in the bottom sight glass. 

(ii) Observing clear water only gushing from the sample 
point . 

(iii) Noting a marked increase in the flow of return 
water . Wait for this before stopping the transfer 
by stopping the elution water pump locally. This 
is important as the increased flow indicates that 
the carbon transfer line is flushed clear. Again 
do not risk flooding the kiln by over flushing the 
llT *e. 

i. After stopping the elution water pump locally, reset the 
switch and then reset the sequence controller by: - 

<i) On the sequence controller panel, switch the L.H.S. 
toggle switch to "m' and the adjacent toggle switch 
to % out off 1 . 

<ii) Pressing the white "reset' button next to the toggle 
switches. 



Clii) Pressing the blue "start* button and then putting 
the toggle switches back to their original 
positions. 



-17- 



3.7 ElectrowinninK 

a. General 

One bed volume (thirty minutes) after the commencement of the 
elution step (06) the electrowinning cell may be put into 
operation. When a strip is not in progress and the cell is 
required to electrowin intensive cyanidation product, at 
least 15 cubic metres of hot water should be pumped from the 
column into the eluate tank beforehand, 

b. Start Up Procedure 

(i) Check the valves by the eluate tank. 

(ii) Shut the drainage valve at the base of the cell. 

<iii) Open the input valve partly. 

(iv) Hake sure that the fume exhaust fan is operating. This 
be left on at all times. 



<v> Start the pump - it will not start if the local switch 
outside the goldroom door has been left isolated. 

(vi) Open fully the input valve. 

(vii) When there is a flow over the weir at the discharge end 
of the cell, switch on the rectifier and adjust the volts 
to no more than 5.0; the amps will be around 600. 

(viii) Regulate the input valve so that the eluate level is 
about half way up the overflow outlet of the cell. 

(ix) Monitor the cell regularly to check on both eluate level 
and volts. 

(x) Check the pH and cyanide levels. They should be around 
12.5 and approximately 0.3% respectively. 

(xi> Tell the night shift personnel that the cell is 
operating. If there is a power failure, the pump will 
need to be restarted at the local switch. 

c . Shut Down Procedure 

(i) Take an eluate sample. The assay should be <5 ppm, /Au 
before shutdown and if there is time, <1 ppm. /Au. 

(ii) Stop the pump - reset the switch immediately, 

(iii) Open the dump valve on the line leading to the eluate 
tank. 



(iv) Vhen the cell is half empty, switch off the rectifier and 
turn the control knob back to zero. 



-18- 



(v> Shut dt open the appropriate valves by the eluate tank, 

<vi) Before pumping out the spent eluate to the process water 
tank, advise both the intensive cyanidat ion operator and 
the shift foreman. 

Cvii) When the tank is pumped out , the eluate pump should stop 
and the low level indicator will come on on the control 
panel. Change the valves by the eluate tank back to the 
positions required for e lectrowinn ing . 



d. Points to Watch 

1. High eluate level in the cell could indicate:- 

(i) The cathodes are blocked with slime or fully 
loaded . 

<ii) The input valve is opened too far. 

2. Low eluate level in the cell could indicate: - 

(i) The pump is faulty, 
(ii) The input valve is shut too far. 

3. Incorrect voltage level could indicate: - 

Ci) Too much resistance in the cathodes, i.e. 
they are heavily loaded or slimed up. 
Cii> Faulty electrical contact on the cell. 
Ciii) Incorrect pH level. 

4. Eluate is poisonous - wear gloves when taking a sample or 
handling the cathodes. Do not linger by the cell even when 
the fume exhaust fan is operating. 




Tu/d Mintek design cells are used here for recovery of 
gold by electrowinning from the eluate. hach cell has nine 
cathodes and these can together load up to 70 kgs. of gold 
Plate on about 3.5 kgs. of steel wool under good conditions. 



-19- 



3, 8 Stripping System - Optimization of Reagent Usage 

a . Desired Reagent Levels 

Acid Wash 

Step 03 2% HCL 

Stripping sequence 

Step 02 2 to 3% NaCN 

Electrowin ....sufficient NaOH for pH 12.5 

b. Control of Reagent Addition 

The reagent addition can be controlled by altering either the 
pump speeds, i.e. by changing the pulleys, and/or adjusting 
the dosing time that has been programmed into the sequence 
controller, Altering of the pump speed is preferable in 
cases where a change in the level of one reagent only is 
desired on a permanent basis. Changing of the dosing time in 
the stripping sequence (step 02) results in the changing of 
the levels of both NaCN and NaOH as the same timer controls 
both pumps. Should it be necessary for some reason to add an 
additional amount of either reagent at the end of step 02, 
e.g. is cases where the pressure relief valve of a particular 
pump is faulty and reagent goes back into the tank, this may 
be done by operating both the particular pump and the 
relevant valves manually. Refer to section 2.4c of this 
manual . 



c . Example Calculation of Reagents Required for Stripping 
Sequence Step 02 

NaCN added 560 litres @ 15% 

NaOH added 100 litres <3 49% 

Volume of column . . 3900 litres 

Bed volume 

(1.9 tonnes) 3600 litres 

of which 0.6 is occupied by aqueous phase. 

Hence in the preheat step <05), available aqueous phase 

= (3900 - 3600 litres) excess space in column. 

+ (0,60 x 3600 litres) aqueous phase in bed volume. 

+ 100 litres in external pipework 

2560 litres. 

NaOH added to preheat 

= 100 litres x 1.5 (sg correction) 
= 150 kgs. 

Since it is at 49%, the total NaOH added 



150 kgs. 



«. = 73.5 kgs . 



-20- 



Level of NaOH in column 

- 73, 5 x 100 = 2.9% 

2560. 

HaCN added to preheat (no sg correction required) 

15. x 560 " 84.0 kgs. 

100. 

i 

Level of NaCH in column 

84. x 10 = 3.3% 

2560. 

Determining Optimum Acid Vash R insing Time 

The acid rinse step (05) is currently set for 2.5 hours. This 
could be excessive and wasting potable water. To determine 
the optimum time it is necessary to take samples every 
fifteen minutes from the rinse discharge line sampling point 
at the top of the acid wash column. 

These samples should be analysed for Ca plus Mg and then the 
totals plotted versus time. When the curve flattens out, the 
rinsing is sufficient (even if the pH is only 4). The 
sequence controller time for step 06 should then be reset to 
the time indicated by the graph. 



-21- 



FAET 4 - THE STRIFFING SYSTEM - FAULT FINDING 



4. 1 Acid Wash 
Problem 



Possible Cause 



b. Acid wash 
start . 



will not 



Carbon does not Ci> Valve AV 401 not open, 

enter column. <ii) Valve AV 414 not open. 

Ciii) Carbon hanging up - put more 
water in hopper, 
(iv) Blocked screen in top of 
column. 

<i> Fill selector switch not on 
manual . 

<i> Valve AV 414 not open. 
Cii) Blocked screen in top of 
column. 

<i> Pump pressure relief valve 
stuck open. 
Cii) Valve AV 404 not open. 
Ciii) Feed valve to pump not open. 
<iv) Blocked inline screen before 
pump. 

<v) Water pump stator damaged. 
Cvi) Acid pump faulty. 

Points to Watch 

1. Clean the inline strainer at the top of the column 
regularly. 



c . Column pressure over 
200 kPa, 



d. No discharge during 
acid injection or 
rinsing 



2. Watch the column pressure - if it exceeds 200 kPa 
screen in the top of the column may need cleaning. 



the 



3. Check the discharge sump during acid injection and 
rinsing. 

4. At the end of the rinse stage the discharge water should 
have a pH level of >5. 



4 . 2 Transfer of Loaded Carbon to Elution Column 
Possible Cause 



Problem — 



— 



a. High elution column Ci) Blocked inline filter bag. 
pressure. ( ii ) Valve AV 415 not open. 

Ciii) Transfer line to potable water 
tank blocked. 



-2Z- 



b. High acid wash 
column pressure, 
(but not elution 
column pressure. ) 

c. No water discharg- 
ing to potable wat- 
er tank. 



(i) Carbon transfer valves AV 406 
and/or AV 422 not open, 
(ii) Carbon transfer pipe blocked. 

(i) Valve AV 415 not open. 
( ii) Water pump feed valve not 
open . 

(iii) Water pump stator damaged, 
(iv) Water pump not running. 



Points to Watch 

1. The filter bag at the top of the elution column should be 
cleaned out after each carbon transfer. 

2. Make sure that the acid wash column is empty at the end 
of each transfer. 

3. Watch the pump pressure - it should not exceed 350 kPa . 

4. Watch for water discharge to the potable water tank 
should start after the elution column fills with water. 

5. Don't forget to take incremental samples from the carbon 
transfer line sample point. 

4.3 Reagent Addition an d Preheat StaRe 

Problem Possible Cause 



a . High column press- 
ure during reagent 
addition. 

b. Reagent pump 
relief valve by- 
passing fluid. 

c. Elution water pump 
cavitating. 



d. Heater stops. 



e. High column Press- 
ure. 



(i) Valve AV 416 not open, 
(ii) Blocked line to eluate tank, 
(iii) Inline filter bag dirty. 

(i) Blocked reagent line, 
(ii) Valve AV 410 not open, 
(iii) Pressure relief valve faulty. 

(i) Blocked screens in bottom of 
column. 

(ii) Dirty heat exchanger plates, 
(iii) Airlock in top of column. 



water 



pump 



not 



(i) Elution 
running, 

(ii) Thermocal pump not running, 
(iii) Thermocal pressure low. 

(i) Temperature at top of column 
too high. (Preheat 

temperature should not exceed 

90 =c> 

(ii) Heat exchanger plates dirty. 



-23- 



Polnts to Watch 

1. Whilst the reagent pumps are operating check that the 
pressure relief valves are not bypassing any fluid and 
that the flow meters are operating. 

2. Check the bottom of column pressure - it should not 
exceed 350 kPa. 

3. Watch the elution water pump pressure relief valve for 
any liquid discharge. 

4. Make sure that no solution is leaking through the carbon 
transfer valve AV 421. 



4.4 Elution and Carbon Cool 



Problem 



Possible Cause 



a. Stable elution temp- (i) Heat exchanger plates dirty 



era t ure be 1 ow 

1 lO^'C from column. 



<ii> Elution water pump flow rate 
too high. 

Ciii) Preheat not brought up to 
desired column top temperat- 
ure - 90°C). 



b. Stable elution temp- 
erature over 
115 C 'C from column. 



<i> Flow rate of water too low. 
<ii) Thermocal temperature too 
high. 



Points to watch 

1. Maximum thermocal temperature should not exceed 125~C. 

2. Throttling valve should be adjusted to maintain bottom of 
column pressure at 300 kPa during the elution. 

3. The elution water pump flow rate should be between 110 
and 120 1/min. 

4 . 5 Transfer of Barren Carbon to Regeneration Kiln Hopper 



Problem 



Possible Cause 



a. High column pressure. <i) Valve AV 421 not open. 

<ii) Blocked carbon transfer line. 



b. No discharge to kiln 
dewatering screen. 



(i) Valve AV 409 and/or AV 412 and 
/or AV 421 not open, 
<il) Elution water pump feed valve 
not open or inline screen 
before it blocked. 



-24- 




-25- 



i 



FART 5 - THE GRAVITY CIRCUIT 



5. 1 General 

The gravity circuit is designed to extract "coarse gold' from 
the recirculating load in the mill grinding circuit and hence 
prevent a build up within that circuit and the eventual escape 
of some of that gold into the C.I.L. tanks and thereon into 
the final tails. (See fig. 4>' 

5. 2 The Spirals 

a. Optimum Operating Conditions 

For the spirals to work efficiently the feed supply must have 
consistent characteristics and be of a constant rate. 
Variations in the flow rate, the feed size distribution and 
percentage solids will have adverse effects upon separation. 
Generally the solids tonnage should give adequate loading of 
the concentrate and middlings areas and the pulp density 
should be low enough to ensure mobility of particles in these 
areas. 



I 



i 



Feed to the spirals may be adjusted by the moving of two 
splitter arms on either side of the cyclone underflow 
discharge box, this altering the volume of the feed passing 
over the splitter screen. (See fig. 5) 



I 






1 — 




\ / 




Cyclone 
U/F dis- \ 
charge boy^ 






r 







To mill 



To splitter ' To mill 
screen feed 

Fig, 5 The Gravity Splitter Box 



Splitter 
arm may 
be moved 
in either' 
direction 

With bungj 
in place 
C/U dischpr 
fills box k 

pulp floWb 

over sides 

i 



The feed may also be adjusted by varying the speed of 
gravity feed pump. This is necessary when the mill feed 
been dropped and it Is impossible to get sufficient feed 
the gravity pump by adjustment of the splitter arms. At such 
times the speed will need to be dropped and the water addition 



the 
has 
for 



l 
I 
I 

i 
i 



-26- 



adjusted to provide optimum feed density. 

The pulp density may be altered by the addition of water, 
before the splitter screen, in the gravity feed pump hopper or 
to the concentrate launder beneath the prima ray spirals. The 
latter option adjusts the density of the feed to the cleaner 
spiral only. 

The Static Distributor <See fig. 6 ) 

The static distributor at the head of the primary spirals 
ensures an accurate division of the pulp stream to the 
spirals. For maximum efficiency a constant head should be 
maintained in the head pot. The head can be adjusted by either 
altering the flow rate from the splitter screen and/or 
altering the annular gap between the head pot and the 
distributor body, by moving the head pot up or down as 
required. | 




The Primary Spirals 

Feed from the splitter screen passes down into the gravity 
feed pump hopper and from there it is pumped to the static 
distributor above six triplex type primary spirals. As the 
pulp passes down these spirals; separaration of particles 
occurs according to specific gravity and the heavier minerals 
progress to the inner profile while lighter minerals are 
forced towards the outer profile, along with most of the water 
and slimes. At the bottom of each spiral layer there are 
splitters which can be adjusted to ensure the optimum recovery 
of * coarse gold' . (See fig. 7) 




The Wilfley Table Requires 
Constant Monitoring. 



-28- 



d. The Cleaner Spiral 

The middlings and tailings from the primary spirals are 

The proportion going to either may be adjusted so as to help 
achieve optimum grinding conditions. P 

The concentrate from the primary spirals is fed on to a duplex 
cleaner spiral. This spiral operates in exactly the same way 
as do the primary spirals. y 

The concentrate from the inner outlet of the cleaner spiral is 

tailin^ C re^ °? J° 25 V±lfley taMe ™ d the middlings and 
mill d?i.h t0 t ^ « ravit y SU »P P^P which feeds info the 

mill discharge pump feed hopper. 

e. Mainten ance of the Sp irals 

(D for ZZt* ° f the * s P irals sil °uld be regularly checked 

-L UI Wear < 

<11) The spirals should be hosed down on a daily basis. 

(iii) The spirals should be adequately flushed before a 
shutdown and then hosed down immediately afterwards 
SO mm to Prevent a build up of solids on the spiral 

— i* the static 

5-3 The Vilfley T.hl. 
a ■ General Description (See fig, r> 



Wash sprays 




corner 



Fig. 8 The Vilfley Table 



-29- 



The Wilf ley table is a standard No, 12 right hand version. It 
is a mechanically operated reciprocating action table, 
consisting of a self -oiling enclosed type of head motion, a 
partly riffled rectangular deck and an understructure with 
tilting device for the table. 

b. The Head Motion 

The head motion is a self-oiling Pitman and toggle type. The 
motion is created by an eccentric shaft acting on the Pitman 
, with one toggle set and the other toggle connected to a yoke 
driving the table through a connecting rod. (See fig. 9) 




Fig. 9 The Head Motion 



This type of motion forms an uneven stroke, slowest at the 
end of the backward stroke and having increased acceleration 
towards the end of the forward stroke. (See fig. 10) 




1. Beginning of Forward Stroke 

2. End of Forward Stroke 

3. End of Backward Stroke 



Fig. 10 The Stroke Pattern 



-30- 



Ad.1 ustment of the Deck 

(i> Longitudinal Level: The inclination of the table 
lengthwise may be adjusted by the raising or 
lowering of the rocker pockets at each end of the 
deck. (See fig, 11) 




Fig. 11 The Rocker Pockets 



<ii) Tilt of the deck; The deck may be tilted sideways, 
i.e. across the riffles, by way of a hand wheel that 
is connected to a gear which drives bolts 

attached the bolsters on which the rockers 
supporting the table are located. <See fig. 12) The 
forward bolster is linked to the main frame by a 
tension bar that removes any vibration from the 
concentrate end of the table. 



Table Frame 



Hand Wheel-* 




Bolster 



Rocker Pocket 



Fig. 12 The Tilting Mechanism 



(ill) Vater VashL The feed edge of the table (See fig- 8) 
has a water spray bar. This water is adjusted so 
to provide a gentle wash across the table. 



-31- 



Act ion of the Table 

The action of the table creates inverse classification and 
stratification, i.e. each mineral of a certain specific 
gravity is arranged according to size. (See fig. 13) 





Riffle 












O'o'p <^. •- 
* O • o c o O' 
O • ' o * o « • * 







Stratum 



Table top 



Fig. 13 Inverse Classification and Stratification 

Due to the motion the bed moves to the concentrate end. As the 
height of the riffles decreases towards this end of the table 
lighter gangue loses the support of the riffles and the wash 
water carries it towards the lower side of the table into the 
tails and this then concentrates the remaining heavy mineral. 
The heavy mineral then moves on to a smooth plane where any 
fine gangue and larger particles easily rolled by water are 
washed from the concentrate. 

Operation of the Table 

Feed to the table should be around 25 to 30% solids. If the 
percentage solids is too high the table may become bogged and 
separation impaired, this resulting in portion of the heavier 
material being allowed to pass directly across the table into 
the tailings launder. Application of wash water should be 
sufficient to provide a gentle, even flow over the table 
without the development of heavy riffles across the deck. 

Notice should be taken of the type of feed presented and the 
table must be adjusted to ensure optimum separation. Slimes 
will require a short, fast stroke with the tilt not far from 
the horizontal whilst coarse feeds will require a long, slow 
stroke with a steep inclination, (tilt) 

The longitudinal level of the deck may also need to be 
adjusted to cater for different feed characteristics. This is 
done by raising or lowering the rocker pockets at each end of 
the table. Very fine feeds (-175/t* ) may require the table to 
be level longitudinally whereas very coarse material may 
require the concentrate end of the table to be up to 19mm 
higher than the feed end. 

If the table is operating properly there should be a notable 
classification of "coarse gold' and the gangue at the 
concentrate end of the deck with the line of separation coming 
along the diagonal ending of the riffles and terminating near 
the concentrate discharge corner of the table. (See fig. 14) 



-32- 




Tails 



Fig. 14 Lines of Separation 

The Quality of the concentrate recovered may be regulated by 
the movement of the splitter above the concentrate launder. 
(See fig. 15)- 




Fig. 15 Concentrate Launder and Splitter 

Maintenance of the Vilflev Table 

(1) The head motion drive box should be kept topped up 
to the required oil level, 

Cii) The rocker arm pockets should be kept free of 
foreign material and topped up with oil. 

<iii) The table should be kept clean, i.e. no build up 
should be allowed. 

<iv) All parts including the drive belts should be 
checked on a regular basis for wear. 



-33- 



5. 4 Starting Up and Shutdown Procedure for the Gravity circuit 

a . Start Up 

<i) Start the gravity sump pump. 

Cii) Start the Vilfley table. 

(iii) Put a bucket below the concentrate launder. 

Civ) Turn on the raw water isolating valve. The 50mm ball 
valve is accessible from either inside the gold room 
or from the first landing on the stairs leading up to 
the stripping plant control panel. 

(v) Ask the mill personnel to put the bung in the cyclone 
underflow discharge box. 

(vi) Turn on the water addition valve above the gravity 
feed pump hopper . 

Cvii) Start the gravity feed pump. 

(viii) Check that the gravity circuit is operating properly. 

It may be necessary to adjust the feed and/or the 
water addition points. 

b. Shut Down 

(i) Ask the mill personnel to take out the bung in the 
cyclone underflow discharge box and also to flush out 
the gravity feed line and pump hopper. It is 
preferable that the flushing continue for five 
minutes at least. 

Turn off the water addition valve above the gravity 
feed pump hopper. 



Ciii) Stop the gravity feed pump. 

(iv) Close the raw water isolating valve, 

(v) Stop the Vilfley table. Mill personnel may do this by 
isolating it at the gold room switchboard - during 
night shift only. 

(vi) Stop the gravity sump pump. 

(vii) Hose down the spirals. 



-34- 



FART 6 ~ PREPARING QF GRAVITY CONCENTRATES FOR SMELTING 

6 . 1 General 

The final concentrate taken off the Vilfley table Is not 
suitable for direct smelting. The " lines of separation* as 
shown in fig. 14 (PartS) are not always clearly defined as 
there is some intrusion of impurities, namely steel, into the 
concentrate zone and likewise some gold finds its way into 
the middlings. It is therefore necessary to include part of 
the middlings with the concentrate in order to prevent loss 
of too much coarse gold back into the circuit via the 
tailings launder. 

Hence before the concentrate can be smelted it must be 
further upgraded. This may be done by purely mechanical 
means, e.g. re-runs over the Vilfley table, but such methods 
will invariably also result in the loss of some gold back 
into the circuit and also require additional labour. 

It is preferable that all of the gold in the Vilfley 
concentrate be retrieved. Two traditional methods of 
achieving this are Amalgamation and Acid Digestion. Both 
methods have been practised throughout Australia for many 
decades and likewise both offer very good recovery if 
efficiently employed. 

6 . 2 Amalgamation 

This method involves the exposure of gravity concentrate to 
mercury in a rotating, fully sealed barrel. The mercury 
amalgamates with any free gold and this product is then 
separated from the remaining waste for later retorting. 
Retorting simply involves the heating of the amalgam so that 
the mercury vaporizes and passes into a condenser barrel 
leaving the gold "sponge' behind. 

This method is extremely efficient but in recent years the 
use of mercury with its associated danger has been frowned 
upon. Hence amalgamation has been rejected as a viable 
alternative here and for this reason it will not be covered 
in detail within this manual. 

6. 3 Acid Digestion 

This method, as used here from the commencement of 
operations, involves the burning away or "digesting' of 
impurities by exposing the concentrate to very strong acid 
solutions. If handled properly it can produce a very pure 
upgraded concentrate for smelting. It is however subject to 
censure on four accounts: - 

<i) It involves the use of highly dangerous acids. 
(ii> The Vilfley concentrate must be upgraded by mechanical 



-35- 



means, i.e. as employed here the re-running of it over 
the Vilfley table, so as to get rid of some of the 
impurities and in so doing reduce the quantity of 
concentrate to an amount that may be efficiently treated 
by acid digestion. 

(iii) Acid digestion does present a security risk in that the 
daily upgraded product is of a very high quality and its 
form is such that some could be very easily "siphoned 
off , 

,(iv) Some loss of free gold may occur during the decanting off 
of acid and subsequent rinsing. 

It is basically for the above reasons that the use of a more 
recent development "Intensive Cyanidation' is being 
experimented with. However as acid digestion has been 
practised for so long here, a step by step procedure has been 
outlined below. 

. Re-run the concentrate for a twenty four hour period over the 
Vilfley table in order to both upgrade the concentrate and in 
so doing reduce it to an amount of no more that 10 to 20 
kilos. 

Expose this in a large container to hydrochloric acid using 
approximately two litres of acid to every kilogram of 
concentrate. Stir regularly. 

Vhen the activity has ceased, decant off the acid, via 
another container, and then rinse the concentrate at least 
four times by filling the concentrate container with water 
and stirring; and decanting off each lot of rinse water. 

Put half a bucket of water into the concentrate container and 
then gradually introduce one bucket of nitric acid. Continual 
stirring is required during this stage and care must be taken 
to prevent frothing over and loss of concentrate. 

Vhen the activity has died down, put the entire 
concentrate/acid solution mixture into the mechanically 
agitated vessel and leave it there for at least ninety 
minutes. This will ensure that all of the concentrate comes 
into contact with the nitric acid. 

Decant off the acid, again into another container. 

Kinse the concentrate thoroughly at least three times; 
decanting off each batch of rinse water into another 
container . 

Should there be any precipitate in the concentrate, this will 
indicate that not enough nitric acid was used. This can be 
easily broken down by exposing it to sulphuric acid. Use a 
50/50 acid/water mix and put the water into the container 



-37- 



first. Only a very small quant it iy of acid is required - 
possibly no more than one to two litres at the most. After 
the precipitate has become entirely fluid, fill the container 
with water and stir well before decanting off the solution 
and rinsing the concentrate. 

i. Dry the concentrate and after recording the weight, lock it 
up in the strongroom. 

Points to Vatch 

1. All of the acids are extremely dangerous! Wear protective 
clothing and a full face mask fitted with a cartridge 
filter suitable for use in areas exposed to organic acid 
fumes. 

2. All of the digestion work must be carried out under the 
fume extraction hood. 

3. Make sure that the water to the scrubber has been turned 
on. 

4. Rinsing between the hydrochloric acid and nitric acid 
applications must be very thorough. The two acids when 
combined will dissolve gold and result in loss whilst 
decanting off, 

5. Any sediment from the containers decanted into must be 
returned to the concentrate container at each stage. 



6 . 4 Intensive Cvanidation 

a. General 

The upgrading of gravity concentrate for smelting purposes by 
use of intensive cyanidation is still in the experimental 
stage. It involves the leaching out of the gold into 
solution, using a strong cyanide mix, and then the 
electrowinning of that solution so as to recover the gold on 
the steel wool cathodes. This system is capable of handling 
all of the initial concentrate off the Vilfley table. 
Because of physical limitations of the present ^pilot plant 1 
it is necessary that the concentrate cut off the Vilfley be 
limited to 100 kilos every twenty four hours, this being the 
optimum amount that can be treated efficiently in the 
leaching vessel. Hence it is necessary for the table to be 
monitored on a regular basis so as to ensure that not too 
much gangue gets into the concentrate, 

b. Description of the Plant (See Fig. 16) 
The Leach Vessel 

This vessel has a capacity of 0.75 cubic metres. It is fitted 
with an air sparge and an air operated agitator that has two 



sets of blades, one set located near the bottom of the vessel 
and the other midway in the optimum charge. The vessel is 
also fitted with baffles and the floor is sloped towards the 
50 mm dump valve, A 25 mm decant valve is located 230 mm from 
the base of the container. 

The Filtration System 

The loaded product from the leach vessel is drawn through the 
decant valve into a primary bag filter (75 microns) and then 
pumped through a secondary bag filter (1 micron), this 
removing most of the foreign material before the solution - 
enters the holding vessel. 

The Holding Vessel 

This vessel is identical to the leach vessel but it has no 
baffles in it and it is not agitated. It allows the accurate 
measurement of the loaded leach and rinse solutions and also 
acts as a storage vessel should it not be convenient to pump 
the solutions into the eluate tank. Solutions from the 
holding vessel may be either gravity fed directly into the 
eluate tank or pumped to it via the filtration system. 

. Operation of the Plant 

Charging the Leach Vessel 

<i) Fill the vessel with potable water to the 300 litre mark. 

<ii) Add 6 kgs. NaCN and agitate for around 15 minutes, 

Ciii) Put in the concentrate - around 100 kgs. 

(iv) If necessary add NaOH to attain a pH level of >11. 

<v) Rote the level of the solution on the vessel. Fill to the 
same level when putting in subsequent leach and rinse 
solutions. 

<vi) Start the agitator, 

(vii) Adjust the air sparge to 10 kPa. 



Optimum Treatment Time 

The duration of each leach and the number of leaches required 
depends largely upon the quality of the concentrate being 
treated. The first leach solution loads up very quickly and 
it is advisable to change it after no more than three hours 
operation. Hence if a charge is put into the leach vessel 
late in the morning it should be changed mid afternoon and 
the final leach left in overnight. Generally only two leaches 
are necessary with the present plant. 



-39- 



Rinsing and Further Leaching 

<i) Stop the agitator and allow the solution to settle. 

(ii) Decant through the filtration system into the holding 
vessel . 

(iii) Note the level on the holding vessel and record it on the 
log sheet. 

(iv) Take a sample and filter it. 150 mis. to go to the 
laboratory for assaying; and the pH and cyanide levels 
to be recorded on the log sheet. 

<v> Fill the leach vessel up to the original mark and agitate 
the solution for 15 minutes. 

Cvi) Check to see what stage the current electrowinning is at. 
If o.k. pump the holding tank out through the filtration 
system, into the eluate tank. 

(vii) Stop the leach vessel agitator and shut off the air 
sparge. After settling, pump the solution into the 
holding vessel. Take a sample for assaying. 

<ix> Fill the leach vessel up again as per section "Charging 
the Leach Vessel" but do not put any additional 
concentrate in and only use 4 kgs. of NaCN, Check to see 
that the pH level is >11. 

Cx) The leach and rinse procedures outlined above are to be 
repeated for the desired number of times. Always be sure 

tfl * ^m ple of both lea nh and rinse solutions, and 

to record the quantities of each, and the pH and cyanide 
levels of leach solutions. 

One rinse must be done between leaches and two rinses 
done after the final leach. 



Dumping of Barren Concentrate 

(i) Open the 50 mm dump valve on the leach vessel. This 
allows the barren material to go back over the VI If ley 
table and ensures that any coarse gold, that has not 
been completely dissolved in the leach vessel, will not 
be able to escape directly back into the circuit. 

<ii) Hose out the vessel and then close the valve. 

Points to Remember 

1. For bullion accounting purposes accurate recording is 
essential. Make sure that the following are completed: - 



(i) Record the quantity of each leach solution. 
Cii) Record the quantity of each rinse solution, 
(iii) Take a sample of every leach and rinse solution for 



2. Record the amount of reagents used for each leach. 

3. Record the operating times. 

4. Close the valves after each transfer from either the leach 
or holding vessel . 

5. Check to see that it is o.k. before pumping out the 
holding tank. 

6. When there is no strip in progress, fill the eluate tank 
with at least 15 cubic metres of hot water from the 
elution column before starting up the electrowinning cell. 
This aids the electrowinning process and also helps to 
ensure that any sludge that may have settled on the bottom 
of the eluate tank is not disturbed. 

7. Check out the filter bags regularly. It is imperative 
that no solids be allowed to enter the eluate tank. 

8. Cyanide and Caustic are very dangerous! Always wear gloves 
and safety glasses when working near the plant. The fume 
exhaust fan should be left operating at all times. 

9. Should there be a power failure during an intensive 
cyanldation process, only go near the plant if it is 
absolutely necessary and make sure that you are wearing an 
appropriate mask, i.e. one that is fitted with a cartridge 
filter suitable for use in cyanide fumes. Remember that 
there is no water for washing in during a power failure. 

10. The pilot plant is located almost directly over the 

barring furnace. Absolute care must be taken when handling 

fluids so as to ensure that they don't splash or seep on 
to the ground floor. 

d. Further Considerations 

Vithin the constraints offered by the physical inadequacies 
of the present leaching vessel, it can be asserted that 
"intensive cyanidation' is a feasible alternative to the "acid 
digesting' of gravity concentrate. However problems are 
occurring as a result of the input of intensive cyanidation 
product into the electrowinning system. The cathodes are 
being clogged up with precipitate and at the time of printing 
this manual, two cells were in operation instead of the 
normal one and all of the cathodes were being changed at 
least twice a week. In the past it has been possible to load 
at least 70 kgs. of gold on to one lot of cathodes in a 
single cell, i.e. nine cathodes, with no ill effects upon the 
operation of that cell. 



This problem will have to be overcome as at present too much 
additional handling of cathodes and cleaning up of sludge 
build up within cells is necessary. In addition the 
subsequent acid digestion and rinsing of loaded wool is made 
difficult by its sludgy nature. Great care is required in 
order to prevent loss of product back into the C.I.L. 
circuit. 

Obviously the benefits of being able to forward the loaded 
solution from intensive cyanidation to the electrowlnning 
system are great in terms of both cost and labour savings. 
Less strips are required each week and this results in 
substantial cutbacks in the use of reagents, water and gas; 
and if the present electrowlnning problems are overcome, a 
high grade product for smelting is ensured. 




Goldroom ForGman, Ron Wilson, demonstrates 
how easy it is to control a heavy container 
on The Granites patented decant platform. 



PART 7 - F PKPABIWG C ATHODE WOOL FOR SMELTING 

7 . 1 General 

diverted to the spare cell. 

7.2 Removing the Vool 

a Dump the solution in the cell by opening the drain valve on 
the line leading back to the eluate tank. 

b. Allow the cathodes to drain for about ten minutes. 

c. Kemove each cathode from the cell and place " £ 
unloading table - ensure that there is a large conxam 
under the discharge slide. 

d. Undo the wing nuts and remove the copper contact bar. 

e. Cut away the section of unloaded wool and put the remaining 
loaded wool into the container. 

f. When all of the cathodes are unloaded, weigh the wool. 
7, 3 Add Dige stion of the Vool 

a. Put on appropriate safety gear - organic acids mask and 
rubber gloves. 

b Place the wool in equal amounts into two large containers and 
place these on the decant platform. (See fig- 17) 

Adding Container 
Sits Inside Tilting 
Deck. 




. 17 The Decant 



-43- 



c. Put a 4:1 mix of HCL and water in each container. Normally 
two buckets to half a bucket in each container. This 
quantity ensures good contact with all of the wool. Put lids 
on the containers. 

d. Stir up the wool regularly. 

e. When the wool has broken up completely, the acid solution may 
be decanted off into buckets. Allow this solution to settle 
before decanting the buckets off into the acid area sump-. 
Retain any sludge left in the buckets. 

f. Fill up each container with raw water, stirring up the wool 
thoroughly as this is done. 

g. Decant off the water into buckets and allow to settle before 
decanting the water into the gravity sump. Retain any sludge 
left in the buckets. 

h. Repeat the rinse/decant process at least three times - the 
rinse water should become quite clear. 

7 . 4 Drying the Cake 

a. Line the large drying tray with newspaper - helps prevent 
cake from sticking to the metal. 

b. Place the tray on the hot plates and switch the controller to 
the * 4 1 setting. Do not put on the top setting as it is 
important that the hot plates don't get red hot. 

c. Place the wool from the final decant in the tray - in an even 
layer. Put any sludge from the decant on top. 

d. Make sure that the fume exhaust fan is operating. 

e. Stir the cake up at regular intervals to facilitate drying, 

f. Do not over-dry; it is better if the cake is left slightly 
damp as this helps prevent the loss of fines, When it is 
dry enough remove the cake from the tray and after weighing 
it, lock it up in the strongroom. Do not leave it outside 
of the strongroom The Granite's C.I.L. cake is virtually 
pure gold/silver - the shrinkage during smelting amounts to 
less than 5% normally. 

g. Switch off the hot plates. 




Latching Mechanism as modified Counter Weights 

by Herman Buhler in accordance with 
design by Ian Williams 




Lifting Device designed and 
made by Herman Buhler. It makes 
the handling of loaded moulds 
much easier. 



FART 8 - SMELTING 



8. 1 The furnace 

A tilting type barring furnace is used. It is heated by L.P. 
gas and the specified maximum rated output of the burner is 
achieved with a gas pressure of 140 kPa. It is presently 
operated an 13 5 kPa, i.e. the maximum attainable pressure from 
our supply system. 

The advantages of using this type of furnace relate mainly to 
safety and ease of handling. The crucible is fully enclosed 
even during the pour hence the risk of injury to the operator 
during a pour is considerably lessened in the event of a 
mishap. Pouring is relatively easy, a virtual one man 
operation provided that the furnace has been properly 




Fig. 18 The Barring Furnace (Inset - Burner Unit) 



The only real problem with this type of furnace is that the 
changing of crucibles is a major task requiring the removal 
of the furnace lid and extensive fireclay work. Smelting is 
normally done of a Tuesday. Should a crucible failure occur 
during the first smelt it would be virtually impossible to 
put in a new crucible in time to get the gold out on 
Wednesday as the furnace must be allowed to cool before doing 
any repair work. 



8 , 2 Crucibles Used 



A 100 graphite based crucibles are currently being used. 
These have been good for about 20 to 25 smelts in the past 
but they are prone to attack by nitre. Of recent months 
around 50% of the gold has come from the gravity circuit and 
whilst the acid digestion of the concentrate from the Vilfley 
table has improved, it has nevertheless been necessary to use 
more nitre when smelting that concentrate. With the 

refinement of the intensive cyanidation system this problem 
will be avoided as most of our gold will be plated out on 
cathode wool. 

However a silica based crucible will shortly be installed. 
These are twice as expensive as the graphite based crucibles 
but with them as much nitre as is required may be used 
provided that there is an excess of silica in the charge. Any 
iron in the charge will combine with silica used in the flux 
to form ferrous silicate. If insufficient silica is used the 
iron will combine with the silica in the crucible and 
eventually cause its failure. 

The normal charge (cake + flux) is usually no more than 
30 kgs. , this assuming that the standard 2:1 (cake: flux) 
mix is used. It is good practice to vary the size of the 
charge as this helps to prolong the life of the crucible. 



8. 3 Moulds Used 



The size of the bullion bars is limited by the capacity of 

the moulds. The moulds used here have a capacity of around 

23 kgs. However for ease of handling within the despatch 

system, it is desirable that the bars do not exceed 19 kgs. 



8 . 4 Fluxes Used 

The fineness of the bars poured here is 
being very little difference between the 
C. I.L. bars and gravity bars in recent 
fluxes used here are : - 



very good, there 
Mint assays for 
months. The main 



Borax 
Boric Acid 
Silica Flour 
Sodium Nitrate 



helps collect iron and i 
agent . 

helps collect iron but 
smelt than borax, 
provides silicon for slag 
collect iron. 
Strong oxidising agent - oxidises iron but 
very damaging on crucibles if used too 
generously. 



good fluidizing 
gives a thicker 
and helps 



Fluidizes slag but works against nitre 



-47- 



Vith the development of the intensive cyanidation system in 
the future it will be possible to use a standard flux mix. In 
the past it has been necessary to use more sodium nitrate 
and silica flour when smelting gravity gold. 

8. 5 Smelting Procedure 

a. Fire up the furnace at least one hour before charging the 
crucible. For the first thirty minutes keep the gas pressure 
below 30 kPa and the air addition regulator closed. Fifteen 
or so minutes before charging turn the gas up to maximum and 
open up the air regulator fully. 

b. Divide up the total cake into convenient smelting lots. Avoid 
having very small smelts. 

c. Mix the fluxes according to desired percentages of each, 
making sure that they are thoroughly blended and all of the 
lumps broken up. Wear a mask and gloves when handling flux. 

d. Mix the cake and flux together (currently 2:1 mix) and then 
pour the total charge into paper bags. This helps to prevent 
loss of fine gold and makes it easier to load the crucible 
when the furnace is hot. 

e. Turn off the flame - do not attempt to load the crucible 
whilst the flame is burning. 

f . Load the crucible and put the cap over the charging hole. 

g. Put the gas on maximum and open the air regulator up fully. 
Put the stirring rod on top of the furnace. 

h. Monitor the smelt regularly. When the charge liquifies it 
will be necessary to stir it at regular intervals. Make sure 
that the rod is red hot beforehand. 

i. Warm up the mould - do not over heat - then position it on 
the sand tray so that it is quite level. 

j. Coat the mould with castor oil just before the pour. This 
prevents the gold from sticking to it. 

k. The smelt will be ready for pouring when the surface goes 
flat and there is no movement, i.e. the charge is in a state 
of ^quiet fusion' . Beware of bubbling around the edge of the 
crucible - it could mean that the charge needs stirring and 
it could also mean that the nitre is eating into the crucible 
wall. The charge will be quite fluid when ready to pour. On 
an average the first smelt takes ninety minutes and every one 
thereafter around sixty minutes. (The furnace has by the end 
of the first smelt achieved its maximum heat. ) 



-48- 



sm^l? i« 2 h 7 C i° thln S and shield and then pour the 
smelt in a steady stream. There must be two p P n p1o present 
at each pour. (For safety and security reasons) ' 

m. Allow the loaded mould to cool until the slag has set. 

^ mould 1 " SlOVSS and Susses - then break the bar out of the 

o. If necessary, immerse the bar in nitric acid 50:50' 
(nitric: water) mix to aid the cleaning process. 

p. Scrub the bar with a wire brush, using soda ash and water. 

^ number ^eV^S^' °S °* the bar and tte 

number, e.g. 0696' on both top and bottom. 

r. Weigh the bar and lock it up in the strongroom. 

t. Clean away the slag after each pour and check for prills 
Any prills found should go into the next smelt. F™"«- 

MoleLn^ *££ reC ° rd thS tor details in the ~Gold 

.J»«* inform the office so that the 

arasfys saKSKsu " check the weishts and lock 

" bo t th t c: Bl lTnat 1 ions Safety **" * *** — lock 

W ' tLrnL h w d * °* eaCh ,. S1Delt check out *»»• crucible 

tiZ^ K 7 rrf- USe the cali P«^s to compare the wall 

thickness with that of a new crucible. 

8.6 Points to Watch 

1. Beware of fumes - these can be extremely toxic 
Fortunately The Granites cake is very clean. 

2 ' smelting"* ° XySen res P^ator before commencing 



3 



Keep liquids away from the furnace. Keep the floor dry. 

4. Keep the goldroom doors locked and make sure that all 

™5 T 5 sl * ned in ' to sure that they fully 

understand the rule, ^hands off. 7 



-49- 



PART 9 - CARBON REACTIVATION 



9 . 1 General 



Fouling of carbon with associated deactivation is fairly 
rapid in C.I, P. circuits. Acid washing and elution only 
partially reactivate carbon and so for its repeated use, 
thermal reactivation after each loading is essential. 
Reactivation kilns are basically of two types; rotary kilns 
and vertical kilns. The use of rotary kilns is widespread 
but generally they have proved to be more expensive in terms 
of capital and maintenance costs and also they offer low 
thermal efficiency, when compared with the more recently 
developed vertical kilns. 

The Granites Gold Mine opted for a vertical type kiln. (See 
fig. 19) Many teething problems were encountered during its 
first eight months of operation. These were mainly 

associated with such things as, difficulty in dewatering the 
carbon prior to its entry into the feed hopper, hanging up of 
carbon in the feed hopper, fouling of the carbon transfer 
heat tubes and poor electronic control. Most of these 
problems have now been overcome. 

Better control of the carbon transfer has ensured a moisture 
content of <50% as per design requirements. This transfer is 
now carried out after the kiln has reached operational 
temperatures, this ensuring that much of the residual 
moisture is vapourized off before it can enter the fire box 
where in the past it has caused considerable damage to the 
insulation. 

The operation of the kiln was impaired for many months 
because of difficulty in maintaining a constant feed. Build 
up on the cone section of the feed hopper interfered with the 
flow of the carbon into the kiln. This has now been partially 
overcome by the cleaning of the metal surface and subsequent 
coating of it with a Teflon film. In addition a small 
vibrator was fitted to the side of the kiln. 

A special reaming device was recently received from The 
United States. When passed through the carbon transfer heat 
tubes it effectively removes all build up and this prevents 
to a great extent the hanging up of carbon within the tubes. 

The electronic controls have now been completely modified. It 
is the desired objective of our maintenance section to make 
the kiln operation completely automatic, i.e. all that the 
operators will have to do is put the carbon into the feed 
hopper, press the " start' button, monitor the temperatures 
and take regular samples for activity testing and finally, 
press the -stop* button. This is of course an admirable 
objective but unfortunately it may not prove to be entirely 
practicable, A feature of this type of kiln is that the rate 




Hxhaust Gas temperature 
thermocouple probe. 



Fire Port 



x. ■ 




Approximate Arrange- 
ment of carbon trans- 
fer heat tubes viewed 
from above. 




Carbon Discharge 
Syntron 



Carbon Temperature 



thermocouple probe 



Sample Taking 
Hatch 



j 



Quench Tank 



Vedge Wire 
Overflow Screen 



— I 



Fig. 19 The Carbon Regeneration Kiln 



-51- 



of carbon movement through it do«5 tend to vary, especially 
during the early hours of each reactivation. During this 
period it is desirable that adj ustments be made to the 
discharge feeder setting and/or to the exhaust gas setting. 
With the present system of controls a change in the discharge 
feeder setting can upset the controls completely. It is 
therefore essential that the operators fully understand 
exactly what each readout display represents and what each 
control does so that they are completely aware of the 
consequences of making any adjustment. 

9.2 Start Up Procedure (See Fig. 20) 

a. If starting from cold, i.e. a new regeneration: - 

<i) Make sure that the feeder switch (on the side of the 
kiln control panel) is in the "on* position and 
that feeder setting is on 5.25. 

<ii) Press the "start' button. 

b. If starting after a "high exhaust gas' temperature fault 
light indicates: - 

(i) Press the black "burner reset' button. 

(ii) Press the "start' button. 

(Ill) Check to see that there is a carbon discharge. 

c. If starting after a "burner fault' light indicates: - 

(i) Reset the black box controller - on the back of the 
burner unit. 

< ii ) Press the "start 1 button. 

(iii) Check to see that there is a carbon discharge. 



9. 3 L. E . D. Readouts 

a. HiRh Exhaust Gas This is a safety device working off the 
exhaust gas thermocouple probe. When the exhaust gas 
temperature reaches the upper limit of the setting, e.g. as 
illustrated on fig. 20 450 + 99~, the "high exhaust gas- 
temperature light will come on and the kiln will shut down. 
Restart as per 9.2b above. 

b. Preheat Temperature Readout 

This is a safety device designed to protect the kiln from the 
impact of sudden heating. The burner will operate on "low 
fire* until the preheat setting, e.g. lOO^C as illustrated 
in fig. 20, is reached. During this period the green light 



-53- 



will indicate alongside the readout, When the preheat 
temperature has been reached this light will change to red 
and:- 

(i) The discharge feeder will start. 
Cil) The "high* fire will come on. 

(iii) The vibrator will operate intermittently as per a 
preset cycle, 

c. High/Low Fire Control 

If the carbon temperature falls below the set point, e.g. as 
illustrated 720-C, the "high' flame will come on. When the 
, temperature reaches the upper limit (720 + lO^C) , the 
"high' fire will go out. The light by the readout will be red 
when the high fire is off and green when it is on. 



■ 4 Shutting Down the Kiln 

(i) For normal "end of regeneration* press the red 
^stop/reset' button at the bottom of the panel. The 
fan only will continue to run for two hours. 

(ii)'For emmergencies only, press the large red 
"emmergency stop' button. Everything including the 
fan, will stop. (Emmergency stop buttons will shortly 
be installed in two positions a safe distance from 
the kiln. The use of these buttons for anything 

other than an emmergency will cause unnecessary 

damage to the kiln and burner unit. ) 



■ 5 Adjustment of the Rate of Carbon Discharge 

(i) Switch the "bottom feeder' switch to "manual'. The 
feeder will then run continuously, 

<ii) Adjust the feeder control setting on the box on the 
side of the kiln control panel. Confirm the rate of 
discharge by taking a physical sample aver 15 seconds 
and multiplying its weight by 0.24 to obtain 
kgs./hour The ideal discharge should be at least 85 
kgs./hour and no more than 110 kgs./hour. 

<iii) Switch the "bottom feeder 1 switch back to "auto* . 

■6 Adjustme nt of Vibrator Intensity 

(i) Switch the (vibrator) switch to "manual' . The 
vibrator will then run continuously. 

Cii) Adjust the vibrator control setting on the box on the 
side of the control panel. 



-54- 



<iii) Switch the ^vibrator' switch back to "auto 1 . 



9. 7 Points to Watch 

a The rate of carbon discharge setting is critical to the 
automatic cantrol mode, A sudden increase in the rate of 
discharge will prompt the ^high' fire to come on and stay 
on as it is governed by a probe in one of the carbon 
transfer heat tubes. This will cause a rapid increase in 
the ^exhaust gas' temperature and could result in a high 
exhaust gas* temperature shut down, 

t 

b. When the exhaust gas temperature readout is very high 
slow the feeder down and monitor the temperature 
continuously. Should it be constantly too high with a 



normal carbon temperature (around 720~C> and likewise 
normal discharge rate, it may be necessary to get the 
electricians to increase the exhaust gas setting. 



readout plus the upper limit should never go above 
580~C. 

c. Should it be suspected that the carbon is sticking up in 
the tubes it is permissable to turn up the discharge 
feeder, e.g. from 5.25 to 5.5, until such time as the 
carbon runs more freely. 

d. Honitor the kiln regularly. Take hourly samples and label 
the combined sample: - 

mrEGEN. NO. STRIP NO. DATE Activity" 

e. Fill in the regeneration log sheet every hour. 

f Do not let the kiln run empty as is is necessary to have 
carbon in the tubes for the next start up The 
regeneration should be stopped when the carbon in the feed 
hopper is just above the drainage gutter. (See fig. W I* 
is not advisable to leave the cone section covered with 
carbon as this may result in a build up on the metal 
surface and subsequent impediment of carbon flow into the 
kiln. It is hoped to have a low level cut out fitted to 
the kiln feed hopper soon. 



-55- 



FART 10 - GOLD ROOM GENERAL 
10.1 Other Goldroom Duties 

a. Loading of cathodes. 

b. Sweeping/hosing of gold plant area. 

c. Maintaining a stock of bullion boxes. 

d. Carrying out repairs to the barring furnace. 

e. Re-stocking of fluxes. 

f. Re-stocking of reagents. 

g. Reaming out of the regeneration kiln heat tubes. 

h. Cleaning of the heat exchanger plates. 

i. Checking of the thermocal level in the expansion tank and 
topping up when necessary 

j. Cleaning of the inline screens before each of the gold 
plant pumps. 

k. Cleaning out of the electrowinning cell, eluate tank and 
potable water tank when required, 

i. Cleaning of screens in both columns and the quench tank 

m. Cleaning out the sump pump pits. 

n. Regular hosing down of the spirals. 

o. End of period stocktakes. 

p. Monitoring of the condition of all plant and seeing that 
the required maintenance is carried out. 



10. 2 Security 

It does not matter how honest employees are, if gold is 
deemed to be missing, ALL persons will be potential suspects. 
Avoid the possibility of this by observing the fallowing 
rules. 

a. Keep the goldroom doors, the strongroom and safe doors 
locked. 

b. Do not leave any cathode cake, gravity concentrate or 



-56- 



smelted products unattended. Lock them up in the 
strongroom when they are not due for immediate handling. 

c. Maintain very precise records of the movement of all cake, 
gravity gold and smelted products. 

d. Maintain very precise records of stripping and in 
particular the intensive cyanidation operations. Vith the 
introduction of intensive cyanidation, daily accountability 

f is difficult. In most instances it will not be possible to 
relate input to output, i.e. head grades with final 
product, until completion of smelting every Tuesday; under 
the past acid digestion system there was a degree of daily 
accountability. 

e. Good sampling is essential! All intensive cyanidation 
leach and rinse batches must be measured and assayed. 
Loaded and barren carbon samples must be taken at regular 
intervals during transfers. Good sampling helps to ensure 
accurate accounting and accurate accounting provides a back 
up if the ^ books don't balance.' 

f . No gold should leave the goldroom without being recorded in 
the ""gold movement' record book; the entry duly witnessed. 
No gold products should be stored outside of the goldroom, 

g. If returning to the goldroom after hours, make sure that 
the shift foreman is aware of your presence, and preferably 
note the reason for and time of your visit in the shift log 
book. 

h. Do not allow any unauthorised person to enter the goldroom. 
All visitors should be entered in the visitors book. 

i. Do not leave your goldroom keys lying around - or allow 
others to use them. (Ninety nine percent of the people 
around this plant would be quite capable of copying them. > 

j. When despatching bullion of a Wednesday morning, keep the 
goldroom doors locked until such time as the bars have been 
signed out and all of the necessary paperwork associated 
with their despatch, completed. Only then should the 
loaded bullion boxes be taken out to the vehicle and the 
security guard should be standing by the vehicle when this 

JO u 

is done. 

k. Maintain radio contact with the gold movement vehicle until 
the gold plane has taken off. 



-57- 



10.3 Safety 

a. Reagents and Fluxes 

This gold plant uses an assortment of reagents and fluxes 
most of which possess same or all of the following 
characteristics: - 

<i> Highly corrosive. 

(ii) Highly poisonous 

<iii) Inflamable - if combined with some other 
reagents or materials. 

<iv) Explosive - when combined with some other 
reagents or substances. 

All employees should read the information sheets at the end 
of this section relating to individual reagents and fluxes. 
They should take particular note of the appropriate first aid 
attention necessary in the case of adverse exposure. 

b. Handling 

Prevention is bettere than cure! Wear appropriate safety 
gear when handling liquid reagents or fluxes. When handling 
liquid reagents, wear rubber gloves and a full face mask with 
appropriate cartridge filter. Far mast goldroom reagents a 
filter suitable for organic vapours is appropriate but when 
handling cyanide a cartridge specifically for use in cyanide 
contaminated areas must be used. 

When mixing fluxes, rubber gloves, safety glasses and 
disposable face mask must be used. Even the most harmless of 
the fluxes, silica flour, (not included in the information 
sheets as it does not possess any of the characteristics 
detailed in section 9.3a> can have serious long term 
respiratory effects if inhaled. 

Extreme care should be taken when drying concentrate or cake. 
The fumes given off can at times be quite toxic or Irritating 
if inhaled. When in doubt wear a mask! Or hold your breath. 



c. General Safety 

(i) Normal safety rules apply within the goldroom surrounds. 
Safety boots must be worn at all times and when working 
outside of the actual goldroom, a safety helmet must be 
worn. Safety glasses must be worn in the proximity of the 
acid and elution columns when they are operating. 



(ii) Good housekeeping is essential at all times. Do not leave 



-58- 



things lying on the floor and clean up all spills 
immediately after they occur. 

(iii) When working on any piece of equipment make sure that it 
has been appropriately isolated and tagged out at the main 
control panel 

(iv) If inspecting "in column screens' or changing heat 
exchanger plates, ensure that all necessary manual valves 
are closed and that any associated pumps are isolated and 
tagged out, 

(v) When working near the furnace on smelting days, full 
protective clothing must be worn. 

<vi> Always wear gloves when handling slag. Even when cold it 
can inflict harm as it may be very sharp. 



i 



I 

I 



I 



-59- 



10. 4 Reagents - Their Effects 



on 



Requiremnets. Handling and Disposal. 



Human Beings. First Aid 



BORAX 



DESCRIPTION 



HAZARDS 

— 7 



White odourless powder. 
Acute poison 



EFFECT 



PRODUCT IN EYE 



Irritant 



PRODUCT ON SKIN 



PRODUCT INHALED 



PRODUCT INGESTED Toxic 



FIRST AID 



Irrigate immediately with 
copious water for 10 
minutes. Seek urgent 

medical attention. 

Vash off with plenty of 
water, removing affected 
clothing and washing 
underlying skin. Clean 
clothing before re-use. 



Remove from exposure, 
warm and at rest. If 
distressed respirator! ly, 
seek urgent medical 

attention. 

Vash mouth out with water 
and give an emetic. Seek 
urgent medical attention. 



HANDLING 
DISPOSAL 



Wear fully protective clothing 
full-face mask with respirator. 



Sweep up, 



gloves 



and 



-60- 



BORIC ACID 



DESCRIPTION 
HAZARDS 



Vliite crystals or powder. 

Toxic by absorption and ingestion. Affects 
central nervous system 



EFFECT 



PRODUCT Iff EVP Irritant 



PRODUCT ON SKIN 



Toxic by absorp- 
tion if in large 
quantities, 



PRODUCT INHALED 



PRODUCT INGESTKD Toxic, nausea, 

vomiting, diarr- 
hoea , shock. 



FIRST AID 



Irrigate immediately for 
10 minutes with copious 
water. Seek medical 

attention. 

Wash off with plenty of 
water, removing affected 
clothing and washing 
underlying skin. Seek 
medical attention. 

Remove from exposure. If 
effects persist seek 
medical attention. 

Vash mouth out with water 

and give water to drink. 

Seek urgent medical 
attent ion. 



i 



HANDLING 



STORAGE 
DISPOSAL 



Wear full protective clothing, 
gloves and safety glasses, 
unnecessary contact. 

Store away from strong alkalis. 

Vash away with plenty of water. 



mask, rubber 
Avoid all 



i 



CAUSTIC SODA 



DESCRIPTION White lumps or sticks 



HAZARDS 



Corrosive on all body tissues, 
water or steam to produce heat 



Reacts with 



EFFECTS 



FIRST AID 



PRODUCT IK EYE 



Severe Burns 



PRODUCT ON SKIN Severe Burns 



PRODUCT INHALED 



Damage to upper 
respiratory tract 
and lung tissue. 



PRODUCT INGESTED Severe burns, Pos- 
sible ulceration. 



Irrigate immediately with 
copious water for 10 
minutes. Seek urgent 

medical attention. 

Wash off with plenty of 
water, removing affected 
c 1 ot h i ng and wash i ng 

underlying skin. Clean 
clothing before re-use . 
Seek urgent medical 

attention. 

Remove from exposure. Keep 
warm and at rest. Seek 
urgent medical attention. 



DO NOT 



induce 



vomiting. 
Wash mouth out with water. 
Seek urgent medical 

attention. 



HANDLING 



DISPOSAL 



Wear fully protective clothing including gloves 
, safety glasses and boots. Avoid breathing the 
vapour . 



Flood with copious water. 



-62- 



HYDROCHLQR I C ACID 



DESCRIPTION 

HAZARDS 
FIRE 

EXPLOSION 



Colourless or pale yellow fuming liquid with 
pungent acidic odour. 

Corrosive liquid and vapour 

Non-Flammable. But gives off toxic fumes when 
heated. Tanks to be kept cool. Safety glasses 
and breathing apparatus to be worn. 

A contact with some metals will cause highly 
flammable hydrogen gas to be given off. 



PRODUCT IN EYE 



PRODUCT ON SKIN 



PRODUCT INHALED 



PRODUCT INGESTED 



EFFECTS 



FIRST AID 



LIQUID : 
Severe Burns 

VAPOUR : 
Burns at high con- 
centration. Irrit- 
ant at low concen- 
trations . 

LIQUID : 
Burns 

VAPOUR : 
Irritation 



High concentrat- 
ions produce con- 
siderable respir- 
atory distress and 
painful coughing. 
Possible lung dam- 
age. Not voluntar- 
ily tolerable. 



Irrigate immediately with 
copious water for 10 
minutes. Seek urgent 

medical attention. 



Wash off immediately with 
plenty of water, removing 
affected clothing and 
washing underlying skin. 
Clean affected clothing. 

Remove from exposure, keep 
warm and at rest. If 
distressed respiratorily , 
give oxygen and seek urgent 
medical attention. 



Systemic 
not known. 



effects 



Seek urgent medical attent- 
ion. DO NOT induce vomit- 
ing. 



HANDLING 

STORAGE 

DISPOSAL 



Vear fully protective clothing, full ; 
with respirator and rubber gloves. 



Do not store 
metals. 



in containers made of 



Avoid contact with liquid. Estinguish source of 
ignition. Flood with water bearing in mind that 
the first run off will be highly corrosive. In- 
form authorities if a major spillage occurs. 



-63- 



L I ME 



DESCRIPTION 
HAZARDS 



White amorphous powder. 

Reacts vigorously with water giving off consid- 
erable heat. Similar reaction with steam, acids 
or acid fumes. 



EFFECT 



FIRST AID 



PRODUCT IN EYE Severe Burns 



PRODUCT ON SKIN Severe irritant. 



PRODUCT INHALED 



Irritant to muc- 
ous membranes 
and upper res- 
piratory tract. 



PRODUCT INGESTED Toxic affects. 



Irrigate immediately with 
copious water for 10 
minutes and seek urgent 
medical attention. 

Vash with plenty of soap 
and water . Remove affected 
clothing and clean before 
re-use. 

Remove from exposure. Keep 
warm and at rest. If 
distressed respiratorily , 
seek urgent medical 

attention. 

Vash mouth out with water 
and give plenty of water to 
drink. Seek urgent medical 
attention. 



HANDLING 
DISPOSAL 



Wear f ul 1 protective 
and safety glasses. 

Flush away with water. 



gloves 



-64- 



KJ1ICACID 



5ISCRIPTI0K 

HAZARDS 

■ 

FIRE 



Colou r le ss or yellowish fumlng 

-acts wifh wate^o f ££Wtio.. 
Non-Combustible. 



EFFECTS 



FIRST ATP 



PRODUCT Iff EYF o 

XJt nx ± Severe Burns 



^ODUOLOILSKIN Burns 



?5B82£T — INHALED Irritant - will 

cause pulmonary 
damage . 

PRODUCT WSSmSZ Severe internal 

irritation. 



Irrigate immediately with 

se^kin* ^ WatSr Whlle 
attention. UrSSnt "* d± °** 

Vash with plenty of warm 
re ^ving affected 
clothing and cleaning 
before re-use. Seek urgent 
medical attention. S 

warT* ex P osu ^. keep 

warm and at rest. Seek 
urgent medical attention. 

with ^waLr ^ th -° UShly 
wa^er. and seek 

urgent medical attenti, 



on. 



HANDL I NG 



DISPOSAL 



SSr^n^SiS "*^! powd — —bid.., 

all combustible^ Z ^^nic acid and 
oxidisable materials ° ther ™*«ily 

Spread soda ash, if avail* hi- 

and m op up cautiously with w!;= ° V S r the are * 

and continue diluting rtti Z f " EUD to wast « 

8 wlth running water. 



-65- 



SODA ASH 



DESCRIPTION 
HAZARDS 



White odourless crystalline powder 
Poisonous if taken internally. 



EFFECT 



PRODUCT IN EYE Irritant 



PRODUCT ON SKIN Blisters? 



PRODUCT INHALED Irritant 



PRODUCT INGESTED Poisonous 



FIRST AID 



Irrigate immediately with 
copious water for 10 
minutes. 

Wash off with plenty of 
water, removing affected 
clothing and cleaning 
before re-use . 

Remove from exposure, keep 
warm and at rest. If 
distressed respirator i ly, 
seek urgent medical 

attention. 

Wash mouth out with water, 
give water to drink. Seek 
urgent medical attention. 



HANDL I NG Avoid dust 



DISPOSAL 



Mop up with water and run to waste, diluting 
with water. 



-66- 



SQDIUM CYAN IDE 



DESCRIPTION 
HAZARDS 

FIRE - 

EXPLOSION 



White crystalline powder 

Emits toxic and flammable vapour on contact 
with acid, acid fumes, water or steam. 

Extinguish with dry powder, alcohol foam or 
carbon dioxide. 

Explosive when decomposing to hydrocyanic acid. 

Reacts violently with nitrite and nitrate. 



EFFECTS 



PRODUCT IN EYE 



Corrosive 



PRODUCT ON SKIN 



Irritant and may 
cause secondary 
infection. 



PRODUCT INHALED 



Poisonous - may 
cause loss of 
appetite, head- 
ache, nausea, 
dizziness and 
upper tract irr- 
itation. 



PRODUCT INGESTED Highly poisonous 



FIRST AID 



Irrigate immediately with 
copious water for 10 
minutes. Seek urgent medic- 
al attention. 

Wash with plenty of water, 
removing affected clothing 
and washing underlying 
skin. Clean clothing before 
re-use . 

Remove from exposure. Keep 
warm and at rest . Seek 
urgent medical attention. 



Induce vomiting and seek 
urgent medical attention. 



HANDLING 



DISPOSAL 



Wear rubber 
respirator . 



No 



aprons, 
smoking, 



rubber gloves and 



Sweep up. DO NOT flush with water. 



-67- 



SODIUM NITRATE 



DESCRIPTION 
HAZARDS 



Colourless, odourless crystals with a slightly 
bitter taste . 

Explosive when mixed with finely divided 
combustible materials, cyanides, sodium 

hypophosphite . Highly toxic when ingested. 



EFFECT 



FIRST AID 



PRODUCT IN EYE Irritant 



PRODUCT ON SKIN Irritant 



PRODUCT INGESTED 



Gastro-enterit is 
.abdominal pains 
, vomiting, musc- 
ular weakness, 
irregular pulse, 
convulsions and 
col lapse . 



Irrigate immediately for 10 
minutes with copious water. 
Seek medical attention. 

Wash off with plenty of 
water, removing affected 
clothing and washing 
thoroughly before re-use . 
If effects persist seek 
medical attention. 

Wash mouth out with water 
and give an emetic. Seek 
urgent medical attention. 



HANDLING 
STORAGE 
DISPOSAL 
FIRE FIGHTING 



Wear full safety clothing, mask, rubber gloves 
and safety glasses. Avoid dust inhalation, 

Store in a dry place away from strong reducing 
agents and organics. 

Sweep up and wash spillage area thoroughly with 
water. 

Ignites on friction when mixed with organic 
material. Use water spray extinguisher and 
W6 3 r 



-68- 



REFBRBNCBS 

Clyde Carruthers Handbook 

"Operation, Maintenance and Installation Instructions for Clyde 
Vilfley Concentrating Table No, 12, Serial Ho. 2143, October 85." 

Comsteel Vickers Limited (Fine Hinerals Engineering Division) 
"Installation and Operations Manual for Vickers FG Spirals and 
Vickers Static Distributor, November 85." 

Kleenheat Gas Handbook 

"Operating Instructions for Vest farmers Kleenheat Gas Pty. Ltd. 
Gold Melting Furnace - Tilting Type." 

Mount Percy Mining Services Pty. Ltd. 
"Operations Manual." 

Western Australian Mining and Petroleum Research Institute Report 
No . 2 . 

"Carbon-in-Pulp Gold Processing Technology - Project No. 10."